Skip to main content

Coal mill overhauling works

Grinding Roller Coal mill overhauling works

Scope of works-----

1. Rollers Housing shaft bearing condition checking
2. Rollers tyres replacement
3. Classifier cone and body welding metal-up where required
4. Mill body inner liner plate or wear plate correction
5 Loading frame and roller centering adjustment work
6 Checking seal air pipe condition
7 Replacement of  Bowl ring and re-tight properly
8 Dynamic ring if damage than replace it otherwise metal up by welding on more wear areas
9 Hard facing welding apply on static ring and other grinding areas with N6006 electrodes
10 Mill gear box and motor coupling alignment
11 Fill roller housing oil level in the range 380mm to 460mm
12 Mill main gear box oil level maintain
13 all leakage control gas kits and sealing rope replace.
14 Coal outlet pipe repairing work using putty or any other type of wear guard materials
15 Scraper shoes gap maintain up to 8mm.
16 Feeder outlet chute repairing works here apply welding electrodes L-308 , this electrodes using ss to ss materials welding
17 Re assemble all de assemble parts
18 Take trial and attend faults, leakage points.
19 After ATT completion mill ready for trail.

Coal mill overhauling video







Comments

Popular posts from this blog

Condensate extraction pump in thermal power plant

WHAT IS CEP (CONDENSATE EXTRACTION PUMP) -  This pump is in actual efficiency booster in a thermal power plant. As we all know that very high temperature and pressure steam expands in a steam turbine and this expanded(low pressure and low temp) steam can go waste if CEP doesn't perform it's function. CEP pump circulate the -Condensate(conversion of steam into water in condenser) again into deaerator tank which prevent plant from a huge loss of water. This water can be used for making deaerator level. Condensate Extraction Pump, as the name suggests the CEP is required to extract the condensate from the Condenser. Condenser is the equipment where all the steam gets condensed and the condensate is extracted out of the same by CEPs. so where the Condensate goes after coming out of the condenser, so it goes to the DEAERATOR by moving through a series of LP heaters, where the temperature of the extracted condensate is increased to a certain degree. In deaerator the soluble gases are...

Coal Firing Burner in thermal power plant

    COAL FIRING BURNER IN THERMAL POWER PLANT

Boiler tube

                         THERMAL POWER PLANT BOILER TUBES A  water tube boiler  can be defined as a Steam  boiler  in which the flow of  water  in the  tubes , as well as hot gases, enclose the  tubes . Not like fire  tube boilers , this  boiler  attains high-pressures, as well as high-steam capabilities, can be achieved. The  steam  generators of the  660 MW  units would be 100%  coal  fired and would be rated to generate about 2170 t/hr each, of superheated  steam  at about 250 kg/ cm2 pressure and 568°C temperature. Reheat  steam  temperature would also be 568°C. Boiler Erection of Water Tubes...... How do I find a leak in my boiler tube? For detecting  boiler tube  leaks, plant operating engineers constantly monitor  boiler  furnace vacuum, which is maintained between a -10 to -20 mm water column...